Sunday, April 24, 2016

Risk Categories & Risk Break Down Structure

Risk Categories


1. Technical
       Requirements, Technology, Quality
2. External
       Suppliers, Regulators, Market
3. Organizational
       Resourcing, Funding
4. Project Plan
       Estimating, Planning, Controlling


Risk Break Down Structure (RBS)

RBS could be defined as a "hierarchically organized depiction of the identified project risks arranged by risk category."



The purpose of the risk breakdown structure (RBS) is to encourage people to think of risks that may originate outside of their “stovepipe.” Most people will think of the specific risks, often technical risks, that are impeding their getting their specific assignment done, and it is good to identify those risks. However, project team members have been involved with the project and have seen risks to success arising from other causes. In particular, external elements including regulators or the customer may be causing problems with the project. And there are barriers to success from the performing organization as well. These particular risks may be unpopular to discuss and to recognize, so the RBS helps people confront those sources of risks.

The risks should be discussed in a structured way, such as:
Because of (some cause that is true),
a risk (an uncertain event or condition that, if it occurs will affect an objective in a positive or negative way),
leading to (an impact, sometimes a range of possible impacts on a project objective). 

Distinguishing a risk from its cause and impact is important so that a mitigation of the true risk can be developed. For instance, do not say; “We have 12 schedule risks.” We might say, we have 4 external risks that affect schedule if they were to occur, distinguishing the source of the risk from its impact. Also, do not say; “Our risk is that the mineral deposit is in an inaccessible location in a mountainous jungle.” That fact may be a cause of logistical risks, but it is not an uncertainty at all.





Saturday, August 9, 2014

Overall Risk

What is Overall Project Risk?
Overall risk is not just adding up the individual risks identified within the project. 
Because there are different sources of uncertainty that could affect the whole project not just the individual risks within the project. 

Overall project risk is an uncertainty that would affect the whole project. 
Some of the individual risks within the project could affect the whole project and they can contribute to overall project risk. But there are other things which are not risks within the project which would include context, the organizational context, the program within which this project sits, the environment that we're delivering our results into, the culture of our own organization under the client organization. So there are many things which are outside the project which contribute to uncertainty of the project as a whole in addition to the risky things within the project that the project manager has to manage through the risk register.

Sources of Overall Project Risk:
Unrealistic deadlines
Project size - larger the project size larger is the overall project risk.
Overall project-level risk factors include:
Inexperience of Project Manager
Weak sponsorship
Regulatory issues
Ineffective project decomposition resulting in inefficient workflow